Construction · Weather and RDOs

Rained off? You are paid for up to 32 hours in four weeks.

When rain, heat, wind or dust make it unreasonable or unsafe to keep working, the On-site award says you do not have to, and pays you for the time lost up to a limit. How the conference works, what agreements add for heat, and how rostered days off accrue, bank and pay out.

A concreter drinks water in the shade on a hot day on site.
32 hoursinclement weather pay in each 4-week period under the On-site award
60 minutesthe most the employer can take to confer once you ask
0.4 hoursa day accrues toward a rostered day off, one every 19 days worked

Check first Check your enterprise agreement first. Many builders' agreements add a temperature trigger and their own inclement weather procedure, and some say you lose the payment if you leave site before the consultation step.

Inclement weather under the Building and Construction General On-site Award 2020 means rain or abnormal climatic conditions (hail, extreme cold, high wind, severe dust storm, extreme high temperature or the like) "where it is not reasonable or it is unsafe for employees to continue working in those conditions" (cl 24.2). It applies to general building and civil construction, not metal and engineering construction (cl 24.1). There is no fixed temperature in the award.

How it works on site

  1. When the employees or their representative ask, the employer must confer within a reasonable time, and no more than 60 minutes, about whether the conditions apply (cl 24.3).
  2. The employer must record when work stops and resumes (cl 24.4).
  3. You are not required to start or continue work where it is unreasonable or unsafe (cl 24.5). Emergency work and finishing a concrete pour already started may continue unless it raises a reasonable concern of imminent risk to your health or safety. A completed pour is paid at 200% to the next hour, with wet weather gear; if you are soaked in a pour and have no dry clothes, you may go home without loss of pay (cl 24.5, 24.6).
  4. Workers on parts of the site that are not affected keep working (cl 24.12). The employer can move you to a safe part of the site or another site, with transport, if there is work in your classification (cl 24.13).
  5. Rain: after more than 4 hours of ordinary time lost in a day, more than half the afternoon, or more than an hour in the last 2 hours, the employer cannot require you to stay on site. You need not walk through rain to a dry area without a covered walkway or proper protection (cl 24.14).

What you are paid

If you cannot work anywhere because of inclement weather, you are paid your ordinary hourly rate for the ordinary hours lost, up to 32 hours in each 4-week period, with pro rata credits for new starters and part-timers (cl 24.7, 24.8, 24.10). Nothing is paid for weather stoppages during overtime (cl 24.11). The ordinary hourly rate includes the industry allowance (see Awards and pay).

Read moreShow less
AwardInclement weather
On-site award (MA000020)Up to 32 hours in each 4-week period (cl 24.7)
Plumbing and Fire Sprinklers Award (MA000036)Up to 32 hours in each 4-week period, credited at the start of each period, not carried over; you must stay on the job until the conference has happened to be paid (cl 21.11)
Electrical Contracting Award (MA000025)Paid for as long as the conditions last, with no 32-hour cap (cl 15.4(a))
Mobile Crane Hiring Award (MA000032)Unpaid unless work stopped by agreement with the employer, but you are not required to work in unsafe conditions (cl 20.1)
Joinery and Building Trades Award (MA000029)No inclement weather clause

Heat

Under the award, "extreme high temperature" stops work only where continuing is unreasonable or unsafe. Agreements usually add a threshold and a procedure. In the sample of builders' agreements:

Read moreShow less
  1. a WA builder's agreement says employees will not work, or be required to work, where the temperature reaches or exceeds 37.5°C (Lendlease WA cl 34.4(g)), and leaving site without consultation forfeits the payment (cl 34.4(f));
  2. a Victorian builder's agreement treats 35°C or more as inclement weather in Greater Melbourne, with a staged procedure using the Bureau of Meteorology forecast (Hutchinson cl 32.3(b));
  3. a NSW builder's agreement adds air pollution and requires the conference within 30 minutes (Multiplex cl 9.8).

Heat clauses are read step by step, in their own words; an old site practice does not override changed wording (see the case below). Work in heat or cold created artificially, above 46°C or below 0°C, earns 20 minutes' paid rest every 2 hours under the award (cl 18.6, 18.7).

Underneath the award and agreement, the safety law still applies: you may stop work if you have a reasonable concern about a serious risk from immediate or imminent exposure to a hazard, and you must not be punished for it. Refusing unsafe work is also a workplace right for general protections purposes. See Safety, falls and stopping unsafe work.

Rostered days off

  1. Ordinary hours are 38 a week, worked as 8-hour days between 7 am and 6 pm Monday to Friday. 7.6 hours are paid and 0.4 hours a day accrue toward an RDO, one every 19 days worked (cl 16.1, 16.2). Time accrues on paid leave and on public holidays not worked (cl 16.3).
  2. RDOs are fixed by a written roster issued 7 days before the 4-week cycle, or by a method agreed by the employer and a majority of employees, and never on a public holiday (cl 16.4). Large projects follow the industry RDO calendar in their agreement.
  3. Up to 5 RDOs may be banked by agreement, and the employer must not unreasonably refuse a request to take a banked one (cl 16.5).
  4. You can be required to work an RDO by agreement, or on at least 48 hours' notice for unforeseen project delays or emergencies. It is paid at Saturday rates and you keep the RDO (cl 16.6).
  5. When you leave, for any reason, accrued and banked RDOs and the hours accrued toward the next one are paid out (cl 16.7). This is a frequent item in final pay disputes.
Read moreShow less

Builders' agreements usually work a 36-hour week instead: 8 hours a day, 7.2 paid and 0.8 accrued toward the RDO, on a calendar fixed in the agreement. When a state declares a new public holiday the calendar can clash: in April 2026 the Commission decided to vary 25 NSW builders' agreements so that 27 April 2026 was a public holiday and the RDO moved to 28 April, with the variations issued separately ([2026] FWCA 934 at [4] to [6]).

Decided cases from construction

What the Commission and the courts decided.

Published decisions of the Fair Work Commission and the courts, retold in plain English from the decision itself. Lawcaptain did not act in these cases. Each links to the full decision.

No right to leave siteFair Work Commission · 12 March 2014

Could the crew walk off at 37 degrees? Only if the agreement's steps said so.

On the new Royal Adelaide Hospital project, the union said afternoon shift workers could leave site once it reached 37 degrees. The agreements' heat clauses had changed.

Read the full storyShow less

Result. The agreements did not give a right to leave at 37 degrees on starting, or after starting at 35 and later reaching 37, except for workers already relocated under the heat procedure; no order made.

A head contractor joint venture was building the new Royal Adelaide Hospital. A formwork subcontractor and the two joint venturers each had agreements with similar inclement weather clauses ([1] to [4]).

The procedure: on a site within a radius of the Adelaide GPO, once it reaches 35 degrees, workers who cannot be moved to a cooler or air-conditioned area go to the amenities building, and relocated workers may leave when it reaches 37 ([61], [77]).

The union argued that workers who start the day at 37, or start at 35, go to the amenities building and then see 37, could leave site. The Commission found no provision supporting that reading. An earlier agreed procedure giving that right had been changed ([85], [86]).

The Commission noted the extreme heat of that summer had tested the clauses, which were written with day work in mind, and proposed a conference about the afternoon shift start time ([87], [89], [90]).

What it means for you

Read your agreement's heat clause step by step: where you must go, when you can be relocated, when you may leave, and whether you are paid. If your agreement has no heat trigger, the award's general test and your right to stop unsafe work still apply.

For employers

If you run a construction business

  • Have a written weather and heat procedure. Record stoppages and restart times, and keep each worker's 4-week inclement weather tally (cl 24.4).
  • Do not dock pay for weather stoppages within the 32-hour allowance. And do not keep workers on site beyond the cl 24.14 limits after they are rained off.
  • Follow the agreement's procedure in its order. A stoppage handled outside the procedure is a pay dispute as well as a safety one. Where the clause is unclear, take it to the Commission rather than docking pay.
  • Track RDO accruals and banked RDOs. They must be paid out when the employment ends (cl 16.7).
For unions and delegates

For unions and delegates

  • The conference is the delegate's tool. Ask for it, and the employer must confer within 60 minutes (cl 24.3). Check the heat trigger in the agreement that applies to the site.
Leading cases

The decisions that set the rules.

Heat clauses in an agreement are read step by step; a changed clause is not overridden by the old site practice.

Questions

The things people ask.

Do I get paid when it rains on a building site?

Under the On-site award, yes, if you cannot work anywhere on the site because of the weather: you are paid your ordinary hourly rate for the ordinary hours lost, up to 32 hours in each 4-week period (cl 24.7). Weather during overtime is not paid.

Is there a temperature at which we stop work?

Not in the award. "Extreme high temperature" counts as inclement weather only where it is unreasonable or unsafe to keep working (cl 24.2). Many agreements add a threshold, for example 37.5°C in a WA builder's agreement and 35°C in Greater Melbourne in a Victorian one. Check yours.

Can I be kept on site after being rained off?

Not after more than 4 hours of ordinary time lost in a day, more than half the afternoon, or more than an hour in the last 2 hours of the day (cl 24.14(a)).

Can I bank RDOs, and are they paid out when I leave?

You can bank up to 5 RDOs by agreement, and the employer must not unreasonably refuse a request to take one (cl 16.5). On termination for any reason, accrued and banked RDOs and part-accruals are paid out (cl 16.7).

My boss wants me to work my RDO. Do I have to?

Only by agreement, or on at least 48 hours' notice where unforeseen project delays or emergencies make it necessary. You are paid Saturday rates and keep the RDO (cl 16.6).

Free discussion · no obligation

Talk to us.

Call 1300 967 552, or leave your details and we will call you.

Do it yourself with AI

General information about Australian employment law, not legal advice about your situation. Updated November 2026.